Meeting Summary from December 6, 2024


Below is a summary of today’s discussions:
  • Project & Planning Update
    • 90% Plans have been submitted to Public Works
    • Floodplain Permit: Preparing for submission. Timeline: 30–60 days. Must be approved before construction begins
    • 10% SIB Requirement:
    • 10% of bid work to go to small or minority-owned businesses
    • Determined by contractor availability (HR&R)
  • ACI Overlay Vote: Scheduled for next Tuesday
  • Alley Parking: Ongoing negotiations with property owner. Owner requests a 2-year contract with opt-out clause. 
  • Seasonal & Site Services Bid Updates for 2025 budget
    • Maintenance contract must be signed before contractor bid is awarded
    • Security Camera System: Estimated annual cost of $18,000
      • Holiday Decorations (Molly):
      • Light poles: Lights, banners, garland
      • Discussion: Buy vs. Rent
      • Jordan Bros. and Heartland Lawns to submit bids by early next year. Won’t do it until 2024 is over.
      • Trash Services:
      • Option for Dale to quote
      • Interim solution: Owners handle trash until permanent service begins
    • Post-Streetscape Community Events (2026): Considering ideas such as a Block Party, Halloween Promotion, Poker Run connecting BIDs or Krampusnacht (holiday-themed winter event)