Friday, September 6, 2024

Meeting Summary from September 6, 2024

Today’s meeting focused on Zoning & Overlay Districts and what that would mean for our BID. The City Planning Department also provided an update on plans.

  • Plan Review & Timeline
  • 75% Plans submitted to BID for review and questions.
  • Urban Planning Board review scheduled for September 20.
  • Maintenance agreements are being revised.
  • Parking easement with adjacent car wash still unresolved 
  • Utility coordination ongoing with OPPD.
  • Anticipated Project Timeline:
  • Bidding: October 2024
  • Final plans: November–December 2024
  • Construction start: Spring 2025
  • Zoning Overlay Purpose
  • Introduces minimum public design standards to align with private business expectations.
  • Focused on addressing urban design challenges in East Omaha, unlike the outdated 1987 Article 22 Urban Design Zoning Code.
  • ACI (Area of Civic Improvement) Overview
  • ACI-1:
  • Most urban and intensive design standards.
  • Includes guidelines for: Roadside Design: Sidewalks, setbacks
  • Site Design: Parking, greenspace, trash areas, signage, utilities
  • Building Design: 
  • Materials, articulation, entrances, design continuity
  • No pole signs; only monument signs (base = 75% of sign width)
  • Standards apply upon redevelopment or major site changes, with possibility of waivers/variances.
  • ACI-2 (e.g., 72nd & Dodge):
  • Emphasizes street landscaping
  • Buildings set back further from the street
  • Zoning Change Discussion: Potential future zoning change from GC (General Commercial) to NBD (Neighborhood Business District) for greater flexibility.
  • Overlay Boundary Expansion: Proposed to include QuikTrip & Russell Speeder’s block Rationale: Area east of 48th on Hamilton would serve as a gateway into the BID