Here’s a summary of our meeting, primarily a 75% Plans & Infrastructure Update:
- Storm Drain Upgrade: Increasing drain size at 48th & Hamilton to 24”.
- Timeline:
- Plans go to drafting by August 23rd. Need to achieve a 0% grade at 48th/Hamilton/Saddlecreek.
- Plans to include final details like road closures and turn lane construction.
- NDOT Permit: Required to occupy the right-of-way at N Saddlecreek & NW Radial/Lafayette.
- Traffic Flow:
- Right-turn lane on Hamilton to be constructed by development team.
- Temporary restriction: No right turn on Hamilton for approx. 6–10 months, but traffic engineer will manage signal timing during this period.
- Emphasis on coordinating construction timeline with public messaging to avoid confusion.
- Goal: Start development construction immediately after streetscape completion.