Friday, June 7, 2024

Meeting Summary for June 7, 2024

During our meeting we discussed: 

  • Temporary Easements: will be required of all businesses along N. Saddlecreek. Will be contacted by the Right of Way (ROW) agent.
     

  • Maintenance Agreement: City attorney is drafting a BID contract for maintenance of the alleyway retaining wall, landscaping, and sidewalks.

  • Funding:

    • OPPD waiver submitted: $455,020 total.

    • Funding includes $285,000 from ARPA and additional fundraising contributions.

  • Traffic & Road Closures:

    • N Saddlecreek closure delayed: policy also requires development completion before turn lane (funded by the developer) is constructed

    • Public input will be sought—having a board at the upcoming public meeting would help.

  • Public Meeting: 

    • Scheduled for June 25 @ Harrison Elementary, 7–8 PM

    • Improved, eye-level streetscape renderings requested

    • Roll plots and corner rendering to be available. 

    • Social media posts planned to promote the meeting.

    • Ollson is mailing out public communications (PC).

  • Street Furniture: Design needs to be finalized soon. Ollson has shared initial concepts with designers and expects updates next week.